kıbrıs ingiltere londra lefkoşa
DOLAR
35,2010
EURO
36,7985
STERLIN
44,3247
BITCOIN
$95.597
Adana Adıyaman Afyon Ağrı Aksaray Amasya Ankara Antalya Ardahan Artvin Aydın Balıkesir Bartın Batman Bayburt Bilecik Bingöl Bitlis Bolu Burdur Bursa Çanakkale Çankırı Çorum Denizli Diyarbakır Düzce Edirne Elazığ Erzincan Erzurum Eskişehir Gaziantep Giresun Gümüşhane Hakkari Hatay Iğdır Isparta İstanbul İzmir K.Maraş Karabük Karaman Kars Kastamonu Kayseri Kırıkkale Kırklareli Kırşehir Kilis Kocaeli Konya Kütahya Malatya Manisa Mardin Mersin Muğla Muş Nevşehir Niğde Ordu Osmaniye Rize Sakarya Samsun Siirt Sinop Sivas Şanlıurfa Şırnak Tekirdağ Tokat Trabzon Tunceli Uşak Van Yalova Yozgat Zonguldak
LONDRA
Hafif yağmur
11°C
LONDRA
11°C
Hafif yağmur
Salı Hafif yağmur
11°C
Çarşamba Parçalı az bulutlu
="http://www.w3.org/2000/svg" viewBox="0 0 300 300" enable-background="new 0 0 300 300">
9°C
Perşembe Kapalı
="http://www.w3.org/2000/svg" viewBox="0 0 300 300" enable-background="new 0 0 300 300">
8°C
Cuma kapalı
="http://www.w3.org/2000/svg" viewBox="0 0 300 300" enable-background="new 0 0 300 300">
8°C

HS2 railway to be delayed by up to five years

HS2 railway to be delayed by up to five years
03.09.2019
0
A+
A-

THE first phase of the HS2 high-speed railway between London and Birmingham will be delayed by up to five years, Transport Minister Grant Shapps says.

That section of the line was due to open at the end of 2026, but it could now be between 2028 and 2031 before the first trains run on the route.

HS2’s total cost has also risen from £62bn to between £81bn and £88bn, but Mr Shapps said he was keeping an “open mind” about the project’s future.

The second phase has also been delayed.

The route – from Birmingham to Manchester and Leeds – was due to open in 2032-33, but that has been pushed back to 2035-2040.

Mr Shapps’ statement was based on a report from the chairman of HS2, Allan Cook, which concluded that the new railway could not be delivered within the current budget.

“I want the House to have the full picture. There is no future in obscuring the true costs of a large infrastructure project – as well as the potential benefits,” said Mr Shapps.

Mr Cook said the delay had occurred because the original plans did not account for the effect of building through densely-populated areas with difficult geographical features.

His report comes ahead of a government decision on whether HS2 will go ahead at all.

Last month, the government said it planned to review the costs and benefits of the rail project, with a “go or no-go” decision by the end of the year.

The government has said that construction work will continue while the review is ongoing.

ETİKETLER: , , ,
Yorumlar

Henüz yorum yapılmamış. İlk yorumu yukarıdaki form aracılığıyla siz yapabilirsiniz.